Difference: AVA (1 vs. 5)

Revision 12006-05-08 - JelenaNinkovic

Line: 1 to 1
Added:
>
>
META TOPICPARENT name="WebHome"

Project status

Phase I:

  • Implantation tests and simulations –done-

Phase II:

simple test structures (single cells, small arrays, front illumination)

  • design finished
  • production started -> April 06
  • Evaluation of test structures -> June/July 06

Phase III:

extended test structures

  • Production of arrays, backside entrance window) -> April 07
  • Evaluation of phase III -> June 07

Production of final structures

-- JelenaNinkovic - 08 May 2006

 