Project status

Phase I:

  • Implantation tests and simulations –done-

Phase II:

simple test structures (single cells, small arrays, front illumination)

  • design finished
  • production finished
  • Evaluation of test structures -> June-November 06

Phase III:

extended test structures

  • Production of arrays, backside entrance window) -> April 07
  • Evaluation of phase III -> June 07

Production of final structures

-- JelenaNinkovic - 08 May 2006